Hamilton Avenue Marine Transfer Station Rehabilitation

500 Hamilton Ave, Brooklyn, NY
New York City Department of Sanitation (DSNY)
10m

Project Overview

This fast-track rehabilitation project upgraded critical structural components at the Hamilton Avenue Marine Transfer Station, improving durability and operational performance within a demanding industrial environment. Completed within a strict 60-day schedule, the work required detailed coordination, efficient construction sequencing, and a strong focus on safety while operating within an active sanitation facility.

Engineer/Designer: HDR Engineering, Inc.

Project Highlights

  • Accelerated construction completed within a 60-day project timeline, requiring precise scheduling and phased work areas.
  • Demolition and reconstruction of heavy-duty tipping floor and loading floor concrete slabs designed to withstand constant truck traffic and high-impact loads.
  • Installation of reinforced concrete topping slabs, structural joints, and heavy-duty finishes to enhance long-term performance.
  • Construction of protective armor walls and structural upgrades within active transfer zones.
  • Careful coordination of staging, material logistics, and workforce movement to maintain operations throughout construction.

Detailed Scope of Work

  • Structural concrete demolition and reconstruction.
  • Installation of reinforced slabs and topping systems.
  • Hopper dump structural improvements.
  • Armor wall construction and protective upgrades.
  • Final restoration completed in accordance with DSNY standards and project specifications.

Hamilton Avenue Marine Transfer Station Rehabilitation: Completed Project

Hamilton Avenue Marine Transfer Station Rehabilitation: During Construction